Next Gen Building Updates
Our mission is to glorify God by making disciples among all peoples:
Nations
Neighbors
And the
NEXT GENERATION.
THE NEXT GENERATION BUILDING
Nations
Neighbors
And the
NEXT GENERATION.
THE NEXT GENERATION BUILDING
- 14 additional classrooms for both church and school that will be filled with students 6 days a week.
- School enrollment can increase to a capacity of 425 students receiving Christ Centered Education.
- Youth ministry expansion: completely renovated loft worship space and cafe area will allow us to serve more teenagers in our Wednesday Night program.
- Kids Ministry and Sunday School: these brand new classrooms will be close to the sanctuary and provide space for all ages to learn and grow.
- An elevator and system of covered walkways will provide handicap accessibility and will connect all of the campus buildings together.

Follow along here for construction updates!
11/3/2025 - Last week we completed the carline expansion to maintain two lanes for carline and the construction fence was moved out to allow for the needed space to work on demolition and foundation work. This week, demolition was completed on Tuesday.
Next Steps - Early next week, the electrician team will begin digging trenches and laying conduit for re-routing power for the campus around the new building foundation. This work will take about 2 weeks to complete, culminating in an electrical power shutdown over Thanksgiving break to reconnect all buildings to the main transformer. The crews will also begin digging out the retention pond in front of the church offices late next week.
Next Steps - Early next week, the electrician team will begin digging trenches and laying conduit for re-routing power for the campus around the new building foundation. This work will take about 2 weeks to complete, culminating in an electrical power shutdown over Thanksgiving break to reconnect all buildings to the main transformer. The crews will also begin digging out the retention pond in front of the church offices late next week.



10/27/2025 - The heavy equipment is here! Demolition work is underway with the concrete wall being removed outside of Dority today. On Tuesday, the carline area will be expanded to allow for two lanes of carline traffic throughout construction. To do this, we had to remove a 3 parking spaces and signs in the asphalt and gravel lot and also a light post that will be relocated in the next few weeks. Once the carline area is finished, the construction fence will be extended into the old carline area to allow space to complete the demolition of concrete and asphalt in front of the Gym. The demolition will continue through this week and next week
Next Steps - Once demolition is complete, the electrician crew will start digging trenches for re-routing electrical cables across campus and start digging the expansion pond along Sawgrass Rd. The dirt from the pond will be used for the building pad.
Next Steps - Once demolition is complete, the electrician crew will start digging trenches for re-routing electrical cables across campus and start digging the expansion pond along Sawgrass Rd. The dirt from the pond will be used for the building pad.



10/20/2025 - Site work has started! This week we are installing stormwater protection measures - silt fence - around the work site. This will be inspected at the end of this week before starting demolition work soon after.
Next Steps - Demolition of the asphhalt area directly in front of the Gym and part of the concrete fence outside of Dority.
Expand the carline area to allow for two lanes throughout construction.
Next Steps - Demolition of the asphhalt area directly in front of the Gym and part of the concrete fence outside of Dority.
Expand the carline area to allow for two lanes throughout construction.

